Construction Update: Curb and Gutter Progress Made

Construction at Rocking Horse Farm keeps humming along, and the latest rumbling involves work on the streets.

Griffin Construction recently began street work at Rocking Horse Farm, and the evidence is taking shape. Curb and gutter is being placed around the farmstead office complex and down to 52nd Avenue. This is the Phase I of the project, which is on schedule to be complete with curb, gutter and asphalt by mid September.

Rocking Horse Farm Pond Takes Shape

An attractive water feature at Rocking Horse Farm recently started to take shape. Excavating, Inc. began digging the retention pond located at the northwest corner of the Second Edition. The Rocking Horse Farm pond is a sizable body of water, and serves a practical purpose of collecting runoff from the 134-unit subdivision. It also gives exclusive waterfront property to 10 building lots, which also enjoy views of the Osgood Golf Course greens and fairways.