Phase I of street construction at Rocking Horse Farm should be completed soon. With the curb and gutter in place, attention immediately shifted to the streets themselves. Crews recently began laying asphalt around the farmstead office complex and down to 52nd Avenue.
Phase II of street construction, which includes the balance of the streets servicing about 81 of the community’s first 136 single-family residential lots, should be complete around October 15 … just in time for the first homebuilders to break ground!